On the morning of November 28, 2013, the inspection team of Henan Provincial Party Committee and leaders of Kaifeng city came to our company for ins...
Good news came from Qilu land on November 23, 2013: designed, manufactured, installed and debugged by our company for KDON (Ar) of Jinan Iron and Ste...
The ability of each person is the prerequisite of whether a person can enter the profession, and also the subjective factor of whether he can be ...
After the cooling device runs for a period of time, the filling pebbles will gradually be compacted and sink due to the impact of air flow back and fo...
On May 30, the 8th air separation plant contract between our company and Linyi Iron and Steel Group officially began to be implemented. This set of K...
Yunnan KDON-3600/8000 air separation plant in Guizhou province. Process features: Two-stage Rectification. Low pressure process...
In order to accumulate the liquid as soon as possible after the appearance of the liquid, we should prepare as much cold as possible and reduce the co...
The following matters should be paid attention to during installation:1) the velocity of oxygen in the oxygen pipeline according to the GB50030-91 &qu...
In the temperature of the forward air into the cooler (hot end temperature, related to the cooling effect of the last cooler of the air compressor or ...
In November 16-18, the appraisal and review group composed of Henan Petrochemical Equipment Management Association conducted appraisal and review on t...
Walking into the factory, you can hear the sound of welding not far away; walking into the work site, those busy figures come into sight. In the hot s...
One-week project progress --- 1500 project of exporting to Burma ● Burma iron and steel company KDON (Ar)-1500 40Y/1500/40Y complete set of air separa...