1) Before entering the site, the project construction organization design shall be reviewed under the leadership of the technical director and submitt
1) All production materials (materials that can be reflected in the budget table and drawings) shall accurately put forward the overall supply applica
1) Before entering the site, the organizational structure of all production personnel and the post division of production personnel should be carefull
1) Implement and improve various management systems and personnel responsibilities.
2) Implement the project management system and the implementation
1) According to the general production plan of the project, arrange the entry plan of the project's machines and tools, and organize the entry of the
1) For the arrangement and preparation of on-site access, the general contractor shall cooperate to achieve "three connections and one leveling" befor
1. arrangement and preparation of site environment
2. mobilization preparation of machines and equipment
3. preparation of the system
5. organizati
It is a kind of evaporative heat dissipation device that uses the principles of evaporation, convection and radiation heat transfer to disperse the wa
A device that uses water as circulating coolant to remove heat.
The exhaust steam discharged from the steam turbine is directly sent to the cooling pipe in the cooling tower through the pipeline. The exhaust steam
A device that uses air as a coolant to remove heat and reduce water temperature.
The compressed air from the gas source contains excessive water vapor and oil droplets, as well as solid impurities, such as rust, sand, pipe sealant,